  • Hello everyone, I want to know, how can I introduce the quantities of a project in primavera P6.

    • 536 Views
    • 1 Answer
    • 0 Vote
    • 536remove_red_eye
    • 1check_circle
    • 0expand_less
    GACEM MESSAOUD on November 21 at 11:25 AM in Planning
  • Dear All AOA I want productivity Standard Productivity Norms ( Production Rates) of Civil (roads, housing, buildings, parks,Infrastructure) , Electrical and Mechanical. Specially If some one ...

    • 569 Views
    • 1 Answer
    • 0 Vote
    • 569remove_red_eye
    • 1check_circle
    • 0expand_less
    sultan Salabat Ahmed on November 20 at 08:33 AM in Planning
  • Mr. Hany Ismael .. how can i deiced or say forthe boss orthe client after i mad the progress steps ( EVM + MH ) , if the project is behind or ahead of Schedule . as a final conclusion

    • 662 Views
    • 1 Answer
    • 0 Vote
    • 662remove_red_eye
    • 1check_circle
    • 0expand_less
    Haytham El-Ansary on November 11 at 04:44 PM in Planning
  • I have around 200 activities with name contains "on site", I need to export the relationships of only these activities in to excel, so i tried to use filter while exporting, filter i need to use is...

    • 1392 Views
    • 2 Answers
    • 0 Vote
    • 1392remove_red_eye
    • 2check_circle
    • 0expand_less
    Asif Mahamood on November 10 at 10:03 AM in Planning
  • Hello Engrs, i want to prepare Structural Steel - Supply and Installation detailed Program of work, with resource loading and cash flow ( Fabricator, Welder, Erector, Etc.) Please advice, Speciall...

    • 592 Views
    • 1 Answer
    • 0 Vote
    • 592remove_red_eye
    • 1check_circle
    • 0expand_less
    Naik N. Nitesh on November 09 at 08:12 PM in Planning
  • When I schedule my project, the start date for the baseline changes with the Data Date. Even though I have assigned the Baseline. Can anybody tell me what's the error I am making?

    • 622 Views
    • 2 Answers
    • -1 Vote
    • 622remove_red_eye
    • 2check_circle
    • -1expand_less
    Ghulam Mustafa on November 08 at 07:08 AM in Planning
    • 774 Views
    • 1 Answer
    • 0 Vote
    • 774remove_red_eye
    • 1check_circle
    • 0expand_less
    wael diab on October 18 at 07:04 AM in Planning
  • Jameel Hayat- Planning Engineer.doc

    • 526 Views
    • 1 Answer
    • 0 Vote
    • 526remove_red_eye
    • 1check_circle
    • 0expand_less
    Jameel Hussain on October 07 at 12:37 PM in Planning
  • Dear Specialists, 1) Any one knows about what is March chart (For pipe line & rail projects )as a planning tool? 2) Which software is good for this ? 3) Any training providers for this? ...

    • 657 Views
    • 2 Answers
    • 0 Vote
    • 657remove_red_eye
    • 2check_circle
    • 0expand_less
    ANIL VARGHESE GEEVARGHESE on October 07 at 08:11 AM in Planning
  • I was recieved a lot of PM schedules from our different clients and that indicate level 1, 2, 3 etc. If any one can explain what it means?

    • 660 Views
    • 1 Answer
    • 0 Vote
    • 660remove_red_eye
    • 1check_circle
    • 0expand_less
    Mubarak N Moideen on September 28 at 07:47 PM in Planning