How can i update 5000 Activity time schedule in primavera p6 ?

I want to ask about is there any fast way or method to update my Primavera p6 time schedule with 5000 activity  ? 

Mahmoud El Refaie on September 07 at 10:33 AM in Planning
Update on a daily basis . I dont think you will have to update 5000 activities at a time.
on September 12 at 07:00 PM
1 Answer(s)
make a filter , 3 weeks look ahead,and then try to sent by email to each responsible discipline or supervisor...then import into P6,or can be updated manually...pending on number of activities,usual shouldn't be more than 50-60 activities ,but pending on reporting cut-off and duration of the project.