Claim Your Free! Membership

How do u measure & compare the progress using primavera?

How do u measure & compare the progress using primavera?
Engr. Mohammad Mallick - MBA. on September 11 at 01:19 PM in Planning
1 Answer(s)
Progress can be measured using EVM earned value management as per the following terms:

Budget at Completion (BAC)
Planned Value (PV) = budget at Completion (BAC) x Planned % Complete
Earned Value (EV) = budget at Completion (BAC) x Actual% Complete
Actual Cost (AC) = No formula What you’ve actually spent on the project
Schedule Performance Index (SPl) = Earned Value (EV) / Planned Value (PV)
Schedule Variance (SV) = Earned Value (EV) – Planned Value (PV)
Cost Performance Index (CPI) = Earned Value (EV) / Actual Cost (AC)
To Complete Performance Index (TCPI) = (Budget at Completion (BAC) – Earned Value (EV) ) / (Budget at Completion (BAC) - Actual Cost (AC) )
Cost Variance (CV) = Earned Value (EV) - Actual Cost (AC)
Engr. Mohammad Mallick - MBA. on September 14 at 12:40 PM