What are the early warning signs you look for when reviewing progress against a schedule?

What are the early warning signs you look for when reviewing progress against a schedule???

Engr. Mohammad Mallick - MBA. on September 12 at 01:49 PM in Planning
2 Answer(s)
Mainly I look for two things. Time and money as follow:
A:Time
planned finish date and forecast finish date. What are the delayed activities. What is critical path.
B: Money
planned value, earned value, what is the most activities with heavy weight.
Hany Ismael on September 21 at 09:56 PM
Actual Finish Date and Total Float
 
-ve Float means Project Delayed
+ve Float Means Project Ahead
 
But you must Consider CPI of the Project with +ve Float.