How to avoid negative float?

How to avoid negative float?

Mahmoud El Refaie on September 07 at 09:53 AM in Planning
1 Answer(s)
We have to commit that dates constrains are fact on the construction projects, however the method of applying these constrains may cause a confusion to the project schedule if we used the imposing tasks to must finish / start by and no later than in primavera.
Mahmoud Omara on September 10 at 03:35 PM
Agree with mahmoud omara in terms of constraint creating negative float. However before you attempt to make any adjustment to those Lags in your schedule, I would suggest that you revisit why there is a need for it. There might be a reason why it is being used. If the only reason for using Lags is to suppress float, thus making the activity critical, then you should remove it and show the real logic of your schedule.