How to copy resource allocation from one activity to another in Primavera P6

How can we copy resources assigned to one activity to another similar activity? For example if we have assigning resources for first slab of a 30 storey building, now how can we copy this resource assignment to the remaining 29 slabs? Or do we have to enter the resources one by one for all the slabs?
 
Thanks
Syed Hasan Shirazi on December 05 at 03:05 AM in Project Management
2 Answer(s)
You cannot copy the resources, but one thing you can do is to assign the resources at the same time by selecting those activities where same resources are being used and then assign them. Select the activities Ctrl+Select.
Bilal Ahmad on January 31 at 09:57 AM